Formation of a Residents Committee on Housing is a key component of a new plan to prepare a ballot measure to rezone enough land for Yorba Linda to meet a state requirement to provide opportunities for 2,415 housing units in the city's 2021-2029 General Plan Housing Element.

A previous rezoning bid failed miserably in November 2022, with 75% of ballots cast against the city's initial plan to meet the state mandate. A public vote on major changes to city zoning documents is required under an initiantive passed by a 299-vote margin in 2006.

The 2021-2029 housing plan was adopted by City Council members in February 2022 and “conditionally certified” by the state's Housing and Community Development department in April 2022. A successful second vote must be held in 2024 to maintain that certification.

Assembling and running a residents committee is the major element in a $50,000 contract with Irvine-based Tripepi Smith & Associates approved by the council at an April 18 meeting.

The committee will hold several meetings over the next few months to develop a revised housing plan with a goal to minimize negative impacts to the community while preserving state certification, Community Development Director David Brantley reported to the council.

Council members also have approved two contract extensions associated with preparing a revised housing element, with the aim of presenting the matter to voters in the November 2024 election.

An existing contract with Pasadena-based Karen Warner Associates has been extended to assist with plan revisions, including adjustments to the site inventory, changes to proposed densities on certain sites and the addition of one or more new sites, Brantley told the council.

The extension is based on “time and materials,” rather than a “set scope of work,” with an hourly rate of $215 for 150 hours and a “not to exceed” cost of $32,250, Brantley reported.

And an existing contract with Irvine-based T&B Planning has been amended to provide for additional technical studies that will be necessary because additional sites will be included in a revised inventory.

These studies will include traffic and noise analysis for a not-to-exceed cost of $128,040. Contract costs and others associated with the housing plan are to be covered from a $650,000 grant from state funds.

Brantley's report noted: “Obtaining and/or retaining state certification preserves local eligibility for numerous state funding programs, insulates the city from related legal challenges and prevents loss of local control due to other mechanisms in place to further the state's interest in solving the housing crisis.”

According to Brantley, such mechanisms include the “builder's remedy” that “allows developers to submit housing developments for 'by right' approval” in cities that don't have a certified housing plan, as well as “suspension of local planning and building permitting authority.”