Yorba Linda: Cielo Vista zoning, library bid award
Two
Yorba Linda City Council actions – pre-zoning for the near 85-acre
Cielo Vista project at the city's northeast border and bid award for
construction of the Lakeview Avenue library and arts center – are
two key decisions as the panel winds up activities for 2018.
The
Cielo Vista property is now in county territory but is in Yorba
Linda's sphere of influence, so eventual annexation is almost
assured. Pre-zoning will allow a planned development that proposes 80
homes on some 42 acres with about 43 acres of open space.
The
council's action does not approve the project but identifies
potential zoning “if and when the property is annexed to the city,”
according to a report from Senior Planner Greg Rehmer.
Annexation
of the property to the city is a multi-step process that will take
from three to four months to complete, Rehmer noted. Initial steps
include the pre-zoning by the city and an application to the county
Local Agency Formation Commission that begins the annexation process.
“The
zoning would then become effective at the same time that the
annexation becomes effective,” Rehmer stated. The city's General
Plan identifies the area as low-density resid-ential and open space,
with an overall density of one unit per acre.
Proposed
property development standards include a minimum lot size of 7,277
square feet; maximum building height of 35 feet or two stories,
whichever is less; 40 percent maximum lot coverage; 10-foot minimum
building separation; and minimum of two covered parking spaces.
The
bid award totals a bit more than $38.2 million for the two-story,
47,800-square-foot library and a one-story, 15,00-square-foot arts
center, with construction to be “substantially complete” by May
2020, according to a report from Max Maximous, the city's public
works director.
Five
pre-qualified contractors submitted bids, with the second-lowest
bidder only $43,000 higher than winner Bernards Bros. Highest bid was
some $40.2 million. An estimate from
the
project's architect was just under $40.3 million.
“Bernard
Bros. has successfully delivered similar civic-related buildings in
both Orange County and throughout Southern California,” Maximous
stated. He cited as “notable” a 98,000-square-foot Newport Harbor
High School building for a theater, library and museum completed on
time and within a $46 million budget.
Council
authorized budget appropriations, inclusive of prior budgeting for
the design phase of about $50.7 million, reflecting full project
budget, including contingency (made up from $25.1 million for the
library fund's contribution; $15.6 million from lease revenue bonds;
and $10 million from a Bastanchury property sale and special
reserves).
Not
included in the bid award were two alternatives involving outdoor
lighting enhancements. One was “festoon lighting” in an “events
meadow” east of the arts center and the other was a lighting design
to accentuate the building facade.